With steel roof framing in place, the new
Academic and Research Center (ARC) is taking on a new
and exciting profile. To see progress as it happens, a
Web-based camera has been installed in the
adjacent Life Sciences Building. Construction progress
now can be viewed at
http://132.235.227.115/
According to Dick Planisek, assistant university
planner, in a July 25 progress report, structural steel
framing is nearly complete on the front (east) half, and
about to go up on the back (west) half. The remainder of
the frames will follow in August.
Ground floor spaces housing mechanical and electrical
rooms are slated to be flood-proofed. Elevator shafts
are in now place, as are ground floor concrete walls.
Meanwhile, construction of an elevated walkway has
begun. The walkway will connect the new building entry
to the West Green Plaza. Enclosed connectors also will
be built to Stocker Center and Irvine Hall.
“Initial plumbing and electrical elements are being
placed—both underground and on the ground floor—as the
structural system allows,” Planisek says. “There will
now be a constant interplay of structural and
mechanical/electrical systems. As this happens, more and
more workers will be on-site.”
The project is registered with the United States Green
Building Council (USGBC) to gain LEED certification, the
recognized standard for measuring building
sustainability. LEED certification promotes design and
construction practices that increase the profitability
of buildings while reducing their negative environmental
impacts.
Ohio University initiated the effort to receive the
certification, which is being handled by the project
architects, Burgess & Niple. OU officials and the
architects are working together to assemble the
necessary information for certification, which is under
review by USGBC, Planisek says.
Slightly behind schedule because of wet weather,
Planisek anticipates that the project will be back on
its original schedule by late fall with the help of
construction crews who are making up for lost time.
“The contractors are expanding their work hours,”
Planisek states. “Both contractors and scheduling
consultants are working diligently to make this happen.”
Planisek says the project team, based on currently
available information, expects the building to be
completed in late 2009, and open for academic use in
January, 2010.
July 2008 Photo Update
Ohio University
College of Osteopathic Medicine
Grosvenor Hall, Athens, Ohio 45701 740-593-4232